WHAT'S HAPPENING AT THE CONSTRUCTION SITE?
Watch for regular updates on the progress of construction. If you have any questions, or if your group or organization would like a presentation regarding the new centre, please contact Laurie Stalker, the Centre's Manager at 780-939-4361 or lstalker@morinville.ca.
Update ~ July 20, 2010
Over the next few weeks, the following site activities are expected:
1. Complete the installation of underslab mechanical se rvices
2. Complete grade beam membrane and insulation
3. Construction of the North Access road expected to continue
4. Drilling of caissons for the High School East entrance and West side parking lot lights
5. Remove existing High School sidewalk and curb
6. Complete south west parking lot work
7. Install remaining piles and pile caps at fron entrance
8. Pour main entrance structual slab