Construction Projects

Upcoming Construction Projects

The projects below are slated to happen in 2025. Anticipated timelines and impacts will be posted when available.

General Infrastructure Construction Projects - 2025

This five-year road rehabilitation project will involve reconstruction of roads, replacement of concrete curbs, gutters, sidewalks and repairs to underground utilities.

  • Locations:97A Ave (from 99 Street to 98 Ave)
  • Timeline: June - October 2025
  • Impacts: If you are a resident living in the affected area, you can expect parking and driveway disruptions for several days during the construction period. Vehicle and pedestrian access will be controlled by flag persons during construction.

This road project will focus on rehabilitation of deteriorating road pavement structure only by means of asphalt overlay.

  • Locations: 100 Street, South of 100 Ave
  • Timeline: June - September, 2025
  • Impacts: Traffic disruptions for several days during the construction period. Vehicle and pedestrian access will be controlled by flag persons during construction.

  • Location: Fish and Game Pond Trail
  • Timeline: August - October, 2025
  • Impacts: Barricaded sections with minimal traffic disruptions.

  • Location: Different locations through the Town
  • Timeline: June - October 2025
  • Impacts: Barricaded sections with minimal impacts

  • Location: Sunshine Lake Park Playground
  • Timeline: August - September 2025
  • Impacts: Sunshine Lake Park Playground will be closed and not accessible during construction.

  • Location: 10125 100 Ave Morinville, AB
  • Timeline: April - September 2025
  • Impacts: Restricted access to some areas of the Townhall lot and intermittent noise from the construction equipment.

  • Location: Different locations through the Town
  • Timeline: June - August 2025
  • Impacts: Barricaded sections with minimal traffic impacts

  • Location: MCCC and MLC Parking Lots
  • Time: September, 2025
  • Impacts: Affected section of the parking lots will be barricaded during construction

This project will cut ditches along the West side of the East Boundary Road to help with the storage and containment of storm water. It will improve the reliability of East Boundary Road and increase resilience against flooding and extensive surface damage, caused by soft, wet subgrades.

  • Location: East Boundary Road (West) - From 96 Ave to Pump House
  • Timeline: November 2025
  • Impacts: Traffic disruptions for several days during the construction period and closure of North portion of MLC Trail

Utility Infrastructure Construction Projects - 2025

  • Location: 107 Street by 99 Ave
  • Timeline: August - September, 2025
  • Impacts: Traffic disruption for several days during construction period

  • Deep Utilities Repairs - In Progress
    • Timeline: June - October 2025
    • Impacts: Barricaded sections with minimal impact

  • Timeline: August 2025 to Feb, 2026

Other Projects

  • Facility Master Plan - (Planning) - In Progress

Future Years - General Infrastructure Construction Projects

Locations: TBD

Road Rehabilitation Map: TBD

 

Future Years- Utility Infrastructure Construction Projects

TBD